3rd Avenue Construction Update
Published on 04/03/2024 • Posted in Neighborhood News, 3rd and 5th Avenues
April 3rd, 2024
3rd Avenue Construction Update
Details
As the paving on 3rd Avenue nears completion, the next steps will be:
- One way-One lane configuration
- Installation of 2 WAY bike path
- Re-installation of speed humps
- Final completion of utility work
- Installation of STOP signs at Encanto Blvd/3rd Avenue
- Finalization of the elements of the traffic circle at Encanto Blvd along with the surrounding 4 corners, protecting the existing palm trees (NE Corner) and completion of the underground utility work.
The above process is slated to take 90 days with July 1st, 2024 target completion.
Thanks for your patience through this process.
Next…expect increased activity on 5th Avenue during April.
Please drive safely.
Bob Cannon