January 2025 3rd/5th Avenues Update
Published on 01/05/2025 • Posted in 3rd and 5th Avenues
3rd Avenue: We are coming down the home stretch on 3rd Avenue now and should be finished by the end of January. Please expect:
- The crystal sand pellets on the green areas will be swept up as the construction clean-up process continues.
- Permanent STOP signs for 3rd Avenue/Encanto Blvd.
- I asked the City to make the parking strips larger and more prominent.
STOP signs are installed. This is a significant traffic pattern change. I watched 12 cars earlier today, and 11 of them did STOP.
(similar signs will be installed on 5th/Encanto Blvd later)
5th Avenue: Buckle up: expect 5th Avenue to be under major construction south of Encanto Blvd over the next 2 weeks. Traffic deviations and closures will occur.
Major construction to continue on 5th Avenue into early 2025. I will post specific details soon. Expect traffic deviations.
As a gentle reminder, the history of this project is on willophx.com under 3rd/5th and on Phoenix.gov 3rd/5th North of McDowell.
Special thanks to all the Willo volunteers who worked on this project over the years.
This project is funded by your tax dollars, and not one penny is financed by the Willo Treasury.
Special thanks to the City and the construction crews who worked over the Holidays.
Also, please drive the speed limit, especially on the 5th during the construction. Be an example, please.
Happy New Year, and thank you for being part of Willo and supporting the Willo Conservation Plan.
Dr. Robert L. Cannon, President Emeritus, 3rd/5th Avenue Chair