3rd/5th Avenues Update – 1/17/25
Published on 01/17/2025 • Posted in 3rd and 5th Avenues
Dr. Cannon,
Here is an update for the activities along 5th Ave.
3rd Avenue
Complete
5th Avenue
Paving activities started this week. As mentioned previously, paving operations is impacted by the colder temperatures that have been experienced this week. As a result, the actual paving has started later in the day which resulted in an extended duration of this activity.
As of today, the project team identified water leaks under the section of 5th Ave south of Encanto Blvd that still needs to be paved. We are coordinating with the Water Services Department for those repairs to be made before paving is complete. Paving is anticipated to resume and be completed early next week. Installation of speed humps will follow the paving operations.
Thanks
Jose M. Rodriguez, PE
Engineering Manager
City of Phoenix Street Transportation Department
Design and Construction Management Division