Here is the update for next week on 5th Avenue. Next week, the striping and signage operations will begin. This may take a few weeks to complete. After striping is complete, the contractor ViaSun will move into completing the delineators along the bike lane and any other minor work to complete the project. Thanks for bearing with us through this home stretch.
1. I asked the City to review the street humps on 5th to ensure consistency with respect to height and width.
2. I reminded the City to ensure McDowell and 5th turn lanes are clearly painted properly.
3. I will discuss some 3rd avenue changes in respect to the Encanto Blvd/3rd intersection at the next Board Meeting.
Also, expect 5th Avenue Encanto Blvd Stop Signs soon.
In closing, if someone want to be on my committee (I am alone) …..I would welcome anyone.