May 22nd, 2025 – 5th Avenue Update from the City as of 5/21/2025

Published on 06/16/2025 • Posted in


Please find below the latest update from the City Traffic Department regarding 5th Avenue.
Thank you, everyone, for your patience as we are coming down the home stretch.
Happy Memorial Day weekend! Special thanks to all our Veterans living in Willo…your service is trulyappreciated.

The City Traffic Services crews are still working on installing signs along 5th Avenue, and this project is expected to continue into next week. Once the City crews are done, Viasun, who is the contractor on the project, will return to complete the few outstanding items, including adjusting the manhole south of Lewis and the installation of the flexible delineators.
The contractor on the project will return to complete the few outstanding items, including adjusting the manhole south of Lewis and installing