Update on 3rd/5th Aves. Construction
Update on 3rd Avenue construction and what is next for 5th Avenue and intersections at Thomas/3rd Ave. Construction on 3rd Avenue will continue for the ...
3rd Avenue Construction Update
April 3rd, 2024 3rd Avenue Construction Update Details As the paving on 3rd Avenue nears completion, the next steps will be: One way-One lane configuration ...
3rd/5th Avenues Construction Notice
Willo has received a new 'Construction Notice' for the 3rd/5th Avenue Improvement Project. This flyer was distributed to 700 households. Construction on 3rd Avenue is ...
Update on Construction Timeline – Response from the City of Phoenix
Good Afternoon Bob, Thank You for your patience while we consulted with the 2 contractors for the projects on 3rd and 5th Avenue. We’ve asked both contractors ...
**UPDATE REVISED** 5th AVENUE DELINEATION PLANS (5th AVENUE DELINEATION ALTERNATIVES)
*5th AVENUE REVISED PLANS* Special thanks to many of you for taking the time to attend the 36-minute Willo Neighborhood Association Meeting on July 27th ...
3rd/5th Avenue Construction Update
3rd Avenue: Construction is moving along, and will now focus on sidewalks on the West Side of 3rd Avenue, finish the roundabout on Encanto Blvd, then ...
Important Update on 3rd/5th Avenue Construction
3rd AVENUE CONSTRUCTION WILL BEGIN BEFORE THE END OF THE MONTH OR SOONER. 5th AVENUE CONSTRUCTION WILL ALSO BEGIN SOON. THE CONSTRUCTION WILL TAKE UP ...
Response letter to Dr. Robert Cannon from Streets Department – Re: green dividers
Bob, Good afternoon. I apologize for the delay in responding to your email and letter. I have been discussing with my team your request in ...
Important update on 3rd/5th Ave Project
For those who attended this morning's Council 4-City of Phoenix Budget Call (special thanks to Board Members, and many other Willo residents for attending today).....our ...